• Latest
  • All
  • Special
  • Spotlight
  • Business
  • Lifestyle
  • India
  • Opinion
  • News
  • Politics
  • Economy
  • Sports
  • Latest
  • Health
  • Nation builder
  • The blitz special
  • Multilateral
  • Perspective
  • Blitz india
  • Latest news
  • Social
  • Rising india
  • A tribute
  • Maharashtra
  • world
  • G20 podium
  • Books
  • States
  • Gender equality
  • Focus uk
  • Eco-focus
  • Entertainment
  • International
  • Legal
  • Econmy/sports
  • Nation
  • world cup
  • Campaign
  • Update
Over 400 road projects are running late

Over 400 road projects are running late, shows report

May 23, 2023
PSG overcome Monaco to advance in Champions League

PSG overcome Monaco to advance in Champions League

February 26, 2026
Ashwini Vaishnaw

Digital platforms must share revenue with media: Vaishnaw

February 26, 2026
Piyush Goyal meets US Commerce Secretary

Goyal meets US counterpart Lutnick

February 26, 2026
PM Modi lauds Netanyahu for wearing Indian attire

India-Israel sign landmark deals in innovation, security & diplomacy

February 26, 2026
Supreme Court observation

Calibrated reform

February 26, 2026
Energy Reforms

India’s expanding role

February 26, 2026
Zverev Crashes Out of Mexican Open

Kecmanovic upsets Zverev in Mexican Open

February 26, 2026
FIIs Pump $2.44B Into Indian Markets

FIIs post highest inflows in markets this month

February 26, 2026
Can't afford delay in using AI, says CEA Nageswaran

India, Sweden sign AI pact

February 26, 2026
Supreme Court

SC issues show cause to NCERT, Depart of Education

February 26, 2026
PM Modi lauds Netanyahu for wearing Indian attire

PM Modi lauds Netanyahu for wearing Indian attire

February 26, 2026
DRAP Targets Zero Dumpsites by 2026 Under Swachh Bharat

Target: Zero Dumpsite

February 26, 2026
Blitzindiamedia
  • Blitz Highlights
    • Special
    • Spotlight
    • Insight
    • Education
    • Health
    • Sports
    • Entertainment
  • Opinion
  • Legal
  • Perspective
  • Nation
    • East
    • West
    • North
    • South
  • Business & Economy
  • World
  • Hindi Edition
  • International Editions
    • US (New York)
    • UK (London)
    • Middle East (Dubai)
    • Tanzania (Africa)
  • Blitz India Business
No Result
View All Result
  • Blitz Highlights
    • Special
    • Spotlight
    • Insight
    • Education
    • Health
    • Sports
    • Entertainment
  • Opinion
  • Legal
  • Perspective
  • Nation
    • East
    • West
    • North
    • South
  • Business & Economy
  • World
  • Hindi Edition
  • International Editions
    • US (New York)
    • UK (London)
    • Middle East (Dubai)
    • Tanzania (Africa)
  • Blitz India Business
No Result
View All Result
World's first weekly chronicle of development news
No Result
View All Result

Over 400 road projects are running late, shows report

by Blitz India Media
May 23, 2023
in News
Over 400 road projects are running late

Team Blitz India

NEW DELHI: The road transport and highways sector has the maximum number of delayed projects at 402, followed by railways at 115 and the petroleum industry at 86, shows the latest flash report on infrastructure projects for March 2023.

The Infrastructure and Project Monitoring Division (IPMD) is mandated to monitor central sector infrastructure projects costing Rs 150 crore and above based on the information provided on the Online Computerised Monitoring System (OCMS) by the project implementing agencies.

YOU MAY ALSO LIKE

PSG overcome Monaco to advance in Champions League

Digital platforms must share revenue with media: Vaishnaw

The IPMD comes under the Ministry of Statistics and Programme Implementation. The report shows that the Muneerabad-Mahaboobnagar rail project is the most delayed – by 276 months.

The second-most delayed project is the Udhampur-Srinagar-Baramulla rail project, by 247 months. The third-most delayed project, Belapur-Seawood-Urban Electrified Double Line, is running 228 months behind schedule.

The Flash Report for March 2023 contains information on the status of the 1,449 central sector infrastructure projects costing 150 crore and above. As many as 821 projects are delayed, 354 reported cost overrun and 247 projects reported both time and cost overrun with respect to their original project implementation schedules.

A total of 821 projects are delayed with respect to their original schedules and 165 projects have reported additional delays vis-a-vis their date of completion reported in the previous month. Of these 165 projects, 52 are mega projects costing ₹1,000 crore and above.

About the road transport and highways sector, the report states that the original cost of implementation of 749 projects was ₹4,32,893.85 crore, but this was subsequently anticipated to cost ₹4,51,168.46 crore.

Previous Post

No pen drives as cyber protocols in place at AIIMS

Next Post

India-made star sensor successful in first space test

Related Posts

PSG overcome Monaco to advance in Champions League
News

PSG overcome Monaco to advance in Champions League

February 26, 2026
Ashwini Vaishnaw
News

Digital platforms must share revenue with media: Vaishnaw

February 26, 2026
Piyush Goyal meets US Commerce Secretary
News

Goyal meets US counterpart Lutnick

February 26, 2026
PM Modi lauds Netanyahu for wearing Indian attire
News

India-Israel sign landmark deals in innovation, security & diplomacy

February 26, 2026
Zverev Crashes Out of Mexican Open
News

Kecmanovic upsets Zverev in Mexican Open

February 26, 2026
FIIs Pump $2.44B Into Indian Markets
News

FIIs post highest inflows in markets this month

February 26, 2026
Please login to join discussion

Economy

FDI limit in public banks may be raised to 49 pc
Economy

FDI limit in public banks may be raised to 49 pc

by Blitz India Media
February 6, 2026

Blitz Bureau NEW DELHI: The Finance Ministry is considering raising the foreign direct investment (FDI) limit in public sector banks...

Read moreDetails
Boosts safety, affordability, and global acceptance

Boosts safety, affordability, and global acceptance

February 6, 2026
AI-for-humanity

AI for humanity – I

February 6, 2026
Public funds for private projects

Public funds for private projects

February 6, 2026
Deserting no more

Deserting no more

January 17, 2026

Blitz Highlights

  • Special
  • Spotlight
  • Insight
  • Entertainment
  • Health
  • Sports

International Editions

  • US (New York)
  • UK (London)
  • Middle East (Dubai)
  • Tanzania (Africa)

Nation

  • East
  • West
  • South
  • North
  • Hindi Edition

E-paper

  • India
  • Hindi E-paper
  • Dubai E-Paper
  • USA E-Paper
  • UK-Epaper
  • Tanzania E-paper

Useful Links

  • About us
  • Contact
  • Team
  • Privacy Policy

©2024 Blitz India Media -Building A New Nation

    No Result
    View All Result
    • Blitz Highlights
      • Special
      • Spotlight
      • Insight
      • Education
      • Sports
      • Health
      • Entertainment
    • Opinion
    • Legal
    • Perspective
    • Nation
      • East
      • West
      • North
      • South
    • Business & Economy
    • World
    • Hindi Edition
    • International Editions
      • US (New York)
      • UK (London)
      • Middle East (Dubai)
      • Tanzania (Africa)
    • Download
    • Blitz India Business

    © 2025 Blitz India Media -BlitzIndia Building A New Nation